Fairview to Wallumbilla Pipeline

Fairview to Wallumbilla Pipeline

Project Type

Location

Commodity

Summary

Design / Engineering Services / Technical Advice

Australia

CSG

130 km pipeline

Santos engaged OSD Pipelines in February 2006 to provide design services and technical advice to support Santos in construction of a natural gas pipeline with metering stations to deliver natural gas from Santos’ Coal Seam Gas field to the Wallumbilla gas hub - a distance of 130 kilometres. At Wallumbilla the pipeline delivers gas from the Santos Fairview CSG Field into the Wallumbilla hub via a connection through the Epic Energy station. From the Epic Energy station the gas flows to market through the Roma to Brisbane and the Ballera to Wallumbilla Pipelines.

OSD Pipelines provided Santos with:

  • Engineering services and design specifications for procurement of pipe, valves and actuators, metering station equipment, telemetry, filters, and scrapers.
  • Engineering services and specifications for construction and testing of the pipeline, inlet station and the outlet metering station which includes nomination and flow control.
  • Engineering services for route selection and Government and landholder approvals.
  • Engineering services as well as facilitation services for risk assessment, HAZOPS and HAZIDS.
  • Engineering services and preparation of design drawings for civil works, piping and isometric fabrication, instrumentation, metering, electrical and lighting  works.
  • Engineering services and preparation of a detailed commissioning plan for the pipeline and metering stations.
  • Engineering assistance during pipeline and station construction and commissioning.

Supply of these engineering services facilitated the successful delivery of a fully functional and commissioned pipeline with inlet and outlet metering stations in March 2007, which was delivered on time and to the clients satisfaction.